Component | Hospitals | Buildings Detailed Cost Estimate in INR Crores | Tender Amount | Status |
---|---|---|---|---|
1 | Government Rajaji Hospital (GRH), Madurai. | 121.80 | 131.76 | Foundation Work 88% completed |
2 | Kilpauk Medical College Hospital (KMCH), Chennai. | 135.50 | 149.54 | Foundation work 79% completed |
3 | Coimbatore Medical College Hospital (CMCH), Coimbatore. | 110.90 | 120.12 | Foundation work 80% completed |
Total | 368.20 | 401.42 |
The equipment list for 3 Tertiary Hospitals has been worked out. Equipment will be procured through Tamil Nadu Medical Service Corporation after obtaining Government Orders.
Current status:The draft list and specification have been prepared. The packaging of equipment is in process. The list and specification will be shared with TNMSC for vetting by 30.07.2021, and will be sent to for JICA concurrence by 15.08.2021. After obtaining JICA concurrence, it will be placed in SEC committee.
The list and specification of Ophthalmology equipment, CSSD, MGPS, MOT etc., are being worked out.
August 2021 | September 2021 |
---|---|
JICA Representative - Site Visited on 03.08.2021 |
JICA Representative - Site Visited on 03.08.2021 |
Safety meeting conducted by the Safety Engineer for the site labours. (dt. 04.08.2021) |
From Mukesh & Associates - DTL Site inspection & progress review meeting on 07.09.21 & 08.09.21. |
CE & EE, PWD visited the site for the discussions on the sump location. (dt. 13.08.2021) |
The Medical Camp was conducted by the Hospital Authority to vaccinate the labourer & staff of the construction project. (dt. 10.09.2021) |
Detailed project display boards in Tamil & English language are provided in the site. (dt. 14.08.2021) |
GF roof slab concrete partially achieved. (dt. 10.09.2021) |
75th Independence Day celebrated at the construction site. (dt. 15.08.2021) |
New EE, PWD - Er. AYYA SAMY has visited the site and reviewed the progress of work. (Dt. 16.09.2021) |
The Quality Control team, PWD visited the site for monitoring the quality and progress of the construction works. (dt. 17.08.2021) |
EE, PWD has discussed with contractor for agreement related queries. (dt. 25.09.2021) |
CE & EE, PWD visited the site for the discussions on the sump location. (dt. 13.08.2021) |
The Medical Camp was conducted by the Hospital Authority to vaccinate the labourer & staff of the construction project. (dt. 10.09.2021) |
First Aid Training Programme conducted by GRH Hospital Authority to the Safety Engineers & Site Engineers. (dt. 18.08.2021) |
For site workers DPH conducted the General health check up. (dt. 29.09.2021) |
Quality Control team, PWD visited the site for monitoring quality and progress of construction works. (dt. 24.08.2021) |
Contractor discussed with Dean, clearance for road side shop hindrance. (Dt. 30.09.2021) |
The Medical Camp was conducted by the Hospital Authority to vaccinate the labourer & staff of the construction project. (dt. 28.08.2021) |
Work progress as on August 2021 | Work progress as on September 2021 |
---|---|
Grade beam & Column, RCC wall form work & Basement level brick work,Staging work for GF-Roof slab Dt. 04.08.2021 |
GF roof slab concrete completed and curing work under progress Dt. 01.09.2021 |
RF-3 Grade beam rebar and column 1st lift form work Dt. 11.08.2021 |
FF Column 1st lift rebar work under progress Dt. 04.09.2021 |
Ramp slab first flight under progress Dt. 19.08.2021 |
GF roof slab concrete work Grid No: X1-X7.1 to Y4.1-Y8 Dt. 10.09.2021 |
Concrete work for GF-Roof slab shuttering and rebars work under progress Dt. 25.08.2021 |
GF Roof slab de-shuttering work under progress Grid no.: X1-X7.1 to Y1-Y3 Dt. 18.09.2021 |
Staircase form work under progress Dt. 27.08.2021 |
Column concrete works - 6 Nos.Grid no.: X6-Y12, Y11.1, X12-Y12.2, X6.1-Y11.1 Dt. 25.09.2021 |
Ground floor roof slab concreting work under progress Dt. 29.08.2021 |
Plinth level brick work & column 2nd lift from work under progress Dt. 30.09.2021 |
August 2021 | September 2021 |
---|---|
Project Director & JICA Representative - Site Visited on 02.08.2021 |
Safety meeting conducted by the Safety Engineer for the site labours. (dt. 01.09.2021) |
Detailed project display boards in Tamil & English language are provided in the site. (dt. 14.08.2021) |
The EE, PWD visited the site for monitoring the quality and progress of the construction works. (dt. 02.09.2021) |
EE, PWD visited the site for monitoring quality and progress of construction works. (dt. 18.08.2021) |
The SE, PWD visited the site for monitoring the quality and progress of the construction works. (dt. 03.09.2021) |
SE, PWD visited the site for monitoring quality and progress of construction works. (dt. 18.08.2021) |
The Quality Control, PWD visited the site for monitoring the quality and progress of the construction works. (dt. 17.09.2021) |
Discussion on Architectural & Structural with PWD Officials, Consultants & Contractors. (dt. 24.08.2021) |
The Medical Camp was conducted by the Hospital Authority to vaccinate the labourer & staff of the construction project. (dt. 25.09.2021) |
Safety meeting conducted by the Safety Engineer for the site labours. (dt. 25.08.2021) |
The EE, PWD visited the site for monitoring the quality and progress of the construction works. (dt. 28.09.2021) |
Discussion on Electrical works with PWD Officials, Consultants & Contractors. (dt. 27.08.2021) |
Work progress as on August 2021 | Work progress as on September 2021 |
---|---|
Pile cap chipping works under progressDt. 04.08.2021 |
Staircase-3 shuttering works under progressDt. 02.09.2021 |
Preparation for Pile Cap-Concrete worksunder progress Dt. 09.08.2021 |
Shear wall 3 & 4 - Reinforcement & Shuttering works under progressDt. 08.09.2021 |
Preparation for Pile Cap-Reinforcement worksunder progress Dt. 11.08.2021 |
Roof Slab - Shuttering works under progress Dt. 14.09.2021 |
Preparation for RCC wall concrete worksunder progress Dt. 23.08.2021 |
Shuttering for ground floor roof slab work under progress Dt. 23.09.2021 |
Preparation for Plinth beam-concrete worksunder progress Dt. 31.08.2021 |
Reinforcement binding for Pile Cap work under progress Dt. 30.09.2021 |
August 2021 | September 2021 |
---|---|
The Medical Camp was conducted by the Hospital Authority to vaccinate the labours & staffs of the construction project. (dt. 28.08.2021) |
The Quality Control team, EE, SDO PWD visited the site for monitoring the quality and progress of the construction works. (dt. 08.09.2021) |
Safety meeting conducted by the Safety Engineer for the site labours. (dt. 25.08.2021) |
The EE & SDO PWD visited the site for monitoring the quality and progress of the construction works. (dt. 17.09.2021) |
Detailed project display boards in Tamil & English language are provided in the site. (dt. 14.08.2021) |
The SE & EE, PWD visited the site for monitoring the quality and progress of the construction works. (dt. 24.09.2021) |
75th Independence Day celebrated at the construction site. (dt. 15.08.2021) |
The Quality Control team / AE PWD visited the site for monitoring the quality and progress of the construction works. (dt. 30.09.2021) |
Work progress as on August 2021 | Work progress as on September 2021 |
---|---|
F8 Raft concrete work under progressDt. 03.08.2021 |
Grade beam GB46, GB38, GB37, GB21A, GB29,shuttering work under progressDt. 01.09.2021 |
Earthwork filling under progress Dt. 07.08.2021 |
Raft concrete & Consolidation and levelling work under progressDt. 04.09.2021 |
CF12 Raft concrete completed.Dt. 12.08.2021 |
Bed lift shear wall and column box fixing work under progressDt. 13.09.2021 |
RF5 column and lift wall Rebar work completedDt. 18.08.2021 |
Raft rebar work under progress Dt. 20.09.2021 |
Soil filling workunder progress Dt. 24.08.2021 |
Column concreting above grade beam under progress Dt. 23.09.2021 |
CF1 & CF13 Raft concrete completed Dt. 28.08.2021 |
Brick work under progress Dt. 30.09.2021 |